Bonjour ,
Nous allons realiser une mise a jour de certains switchs de serveurs et stockage dans le datacentre de RBX.
Cela n'aura pas d'impact sur vos infrastructures Hosts, car tous les serveurs sont double-attaches
Sur les infrasructures Storage, les bascules master/slave seront realisees . une microcoupure est attendue le temps de la reprise d'activite sur le switch slave.
perimetre : Switchs Pcchost
rbx7-pcchost70 programme le 03 septembre 2020 a 07H PM CET
rbx7-pcchost51 programme le 03 septembre 2020 a 07H PM CET
rbx7-pcchost59 programme le 03 septembre 2020 a 07H PM CET
perimetre : Switchs PccStorage
rbx7-pccsto52 programme le 28 aout 2020 a 08H PM CET
rbx7-pccsto36 programme le 27 aout 2020 a 08H PM CET
rbx7-pccsto59 programme le 03 septembre 2020 a 07H PM CET
---------------
Hi,
we will realize a maintenance on switchs of hosts & storage in RBX7.
This operation won't have any impact on your host infrastructure , because we always check if all hosts are double-attached
On storage infrastructure ,there will have some switchover master/slave before starting the maintenance. a micro cut will be done
perimeter : Switchs Pcchost
rbx7-pcchost70 scheduled the September,03th 2020 a 07H PM CET
rbx7-pcchost51 scheduled the September,03th 2020 a 07H PM CET
rbx7-pcchost59 scheduled the September,03th 2020 a 07H PM CET
perimeter : Switchs PccStorage
rbx7-pccsto52 scheduled the august,28th 2020 a 08H PM CET
rbx7-pccsto36 scheduled the august,27th 2020 a 08H PM CET
rbx7-pccsto59 scheduled the September,03th 2020 a 07H PM CET
Update(s):
Date: 2020-09-04 00:31:12 UTC upgrade to switch rbx7-pcchost51 done
upgrade to switch rbx7-pcchost70 done
upgrade to switch rbx7-pcchost59 done
upgrade to switch rbx7-pccsto59 done
Date: 2020-09-03 17:13:44 UTC starting upgrade to switch rbx7-pcchost51
starting upgrade to switch rbx7-pcchost70
starting upgrade to switch rbx7-pcchost59
starting upgrade to switch rbx7-pccsto59
Date: 2020-09-03 17:13:11 UTC upgrade switch rbx7-pccsto36 done
Date: 2020-08-28 18:17:57 UTC starting upgrade to switch pccsto52
Date: 2020-08-27 19:43:14 UTC upgrade switch rbx7-pccsto36 done
Date: 2020-08-27 18:00:02 UTC starting upgrade to switch pccsto36
Posted Aug 25, 2020 - 15:32 UTC
This scheduled maintenance affected: VMware Private Cloud || RBX (Compute).